Sprint Metrics Report

Document Change Control

Release No Release DateIssued ByVersion CommentClickUp Version Time
1.023/1/2025Ahmed ShehataInitial Version Mar 02 11:50 am
2.030/9/2025Ahmed ShehataUpdating MetricsOct 07 2:32 pm

 

List Of Approvers

Name TitleApproved Release No
Tarek Ramadan Software Engineering Director 2.0

Sprint Metrics Report

Project NameEnterprise architecture
Release NoRelease 1
Sprint NoSprint 4
Issue Date1/2/2025
Issued ByAhmed Essam
Reviewed ByAhmed Shehata

 

MetricTargetSnapshotActual ValueRCAComment(s)
Sprint Rework Rate<=10% 17.20%

 

 

Sprint Burn-down>= 95% 27%The team capacity in this sprint was affected by several and long meeting for business release planning

 

Average Cycle Time of US per sprint<= 5 7.75

 

 

Weighted Defect Density (WDD)<= 2 1.2

 

 

Sprint Defect Removal Efficiency (DRE)>= 85% 100%

 

 

 

Recommendations & Actions after Sprint 4

The team capacity in this sprint was affected by several and long meeting for business release planning and unfortunately the next sprint will be affected also→ this predefined with management and need this meeting to get the due date for the release→ This issue must be shared with the management. (SM)